Senergy 2
25MW – Sénégal
Development and commissioning in record time
12 month
150 Jobs
8 months
CO²
27,000 tons of CO2 saved per year (UNFCCC).
25 MW
25 MW installed. Equivalent to the electricity consumption of 200,000 people.
Awarded
Best Renewable Energy Project of the Year 2017 by the Africa IFA.
Project Characteristics
- Project : 25 MWp solar power plant
- Location : Bokhol, Senegal
- Technologies : Polycrystalline modules / Fixed structure / Centralised inverters
- Off-take : 20-year take-or-pay PPP with Senelec
- Construction period : 8 month
- Commissioning : October 2016
- Technical partner : Vinci Energies
The impact of Senergy 2
Substantial savings for the Senegalese State (competitive Kwh price).
Construction of 2 schools and 6 classrooms electrified with solar energy.
150 jobs created during construction and 25 permanent jobs for management and maintenance, of which 40% are reserved for the local community of Bokhol.
As the first industrial-scale solar power plant in West Africa, Senergy 2 required a significant investment, which largely involved Senegalese investors.
On top of Africa REN Grievance Mechanism (in « Contact us »), any person affected by the project and willing to obtain additional information regarding FMO’s Independent Complaints Mechanism can get information on:
https://www.fmo.nl/independent-complaints-mechanism